Waterloo Bridge Staircase Upgrade

Public Realm  

March 5, 2018

The proposed remedial works is divided in 2 phases:

  • Phase 1: Western stair case: March 2018
  • Phase 2: Eastern stair case: June 2018

The scope of works is to carry out some maintenance repair to the stair cases (similar to both sides):

  • Lighting improvement
  • Re-tailing stairs and landings
  • Jet washing the stone wall
  • Cleaning and repair to stone works
  • Hand rail repair & repainting
  • Infilling alcoves (old access to subway, i.e. installing new doors)
  • Infilling ventilation openings